Current City Projects

Hall Sidewalk and Drainage Improvements,  (R-1620)

Projected Start & End Dates – September 2, 2020 – December 29, 2020

Contractor – McCauley Construction, Inc.    

Project Description - The work includes removing the deteriorating sidewalk curb and drainage facilities and installing approximately 800 linear feet of new curb, 6,500 square feet of new sidewalk, ADA ramps, driveways, conduit sleeves, and new drainage infrastructure to facilitate the new sidewalk improvements.  

Project Location - The work shall take place along East Hall from 11th Street to White Mountain Road in Show Low Arizona.   See attached map.


West Cooley and 4th Ave Roadway Reconstruction, (R-0221)

Projected Start & End Dates – September 28, 2020  – December 27, 2020

Contractor – McCauley Construction, Inc.    

Project Description - The work includes the reconstruction of 2,600 LF of roadway including portions of West Cooley and North 4th Ave.  The work includes, but is not necessarily limited to, the pulverization of approximately 7,500 SY of existing asphalt roadway, recycle and mixing existing asphalt millings into existing base, subgrade preparation and compaction, reshaping the roadway grade, installing new asphalt pavement overlay, re-establish roadway shoulder, installation of new drainage culverts, installation new concrete curb and sidewalk, and other items necessary for the accomplishment of the improvement.  The work includes all required labor, material, incidentals, transportation, traffic control, and services required for the project to complete a usable and operable facility in accordance with all pertinent codes and regulations as necessary to complete the job in a workmanlike manner as shown on the Construction and Bid Documents.

Project Location - This work shall take place within the right-of-way along portions of West Cooley from North Central Avenue to North 4th Avenue and in North 4th Avenue from West Cooley to Old Linden Road in Show Low.  See attached map.


West Cooley Sewer Phase II, (S-0521)

Projected Start & End Dates – October 5, 2020 – February 2, 2020

Contractor – Rawlings Specialty Contracting, LLC     

Project Description - The Work includes, but is not necessarily limited to, installing approximately 2,560 LF of new 8-inch PVC sewer line and 8 manholes along West Cooley and connecting roadways from 4th Ave to 8th Ave.   The work also includes removing and replacing any asphalt or concrete to complete the sewer replacement and the installation of new sewer services.  The work includes all required labor, material, by-pass pumping, incidentals, transportation, traffic control, and services required for the project to complete a usable and operable facility in accordance with all pertinent codes and regulations as necessary to complete the job in a workmanlike manner as shown on the Construction and Bid Documents.  

Project Location - This work shall take place along West Cooley and connecting roadways from 4th Avenue to 8th Avenue in Show Low, Arizona, 85901.  See attached map.

 

Cub Lake Road Waterline Replacement, (W-1120)

Projected Start & End Dates – October 12, 2020 – January 10, 2021

Contractor – Apache Underground & Excavating      

Project Description - The Work includes, but is not necessarily limited to, installing approximately 1,750 LF of new 8-inch C-900 PVC waterline, fire hydrants, and required fittings.   Any pavement or concrete removed during the installation of the new line will be replaced.  The work includes all required labor, material, incidentals, transportation, traffic control, and services required for the project to complete a usable and operable facility in accordance with all pertinent codes and regulations as necessary to complete the job in a workmanlike manner as shown on the Construction and Bid Documents. 

Project Location - This work shall take place along Cub Lake Road and Siesta Lane in Show Low, Arizona, 85901.  See attached map.